Beam Delivery Report
Status reports on beam delivery at TRIUMF, and part of the Beam Delivery group's Guide for Experimenters.
Past reports can be found here.
09:03, 8 April 2010 (PDT)
A BIG power bump this morning at about 02:45 knocked everything—RF, main magnet, vacuum—off-line. ISAC had a slew of failures as well. Recovery is underway, but we don't know how long it's going to take. Check the cyclotron and ISAC logs for more information:
We'll update things as we know more. — Morton
20:44, 7 April 2010 (PDT)
Last night's ISIS development ran much longer than expected and resulted in a need for a fair bit of cyclotron tuning. That's why protons weren't restored until this morning. Now that they have been, we're delivering 105/70/55 µA to BL1A/2A/2C4, respectively with µSR experiments running on M9 and M20. PiENu continues to run on M13 while M15 is still being used for testing.
8Li is in the process of being delivered to the βNQR facility at ISAC (about eight hours later than we'd hoped, but still—barely—according to the published schedule). That experiment will run until Monday morning. Otherwise no changes to RIB delivery are expected. The DRAGON group will take stable beam (16O) from OLIS over the weekend to investigate the acceptance of their spectrometer. — Morton
20:58, 6 April 2010 (PDT)
The first long maintenance/ISIS filament change of the schedule is drawing to a close. The plan was to implement a new theoretical tune for ISIS before injection and beam delivery later this evening. Some proton beam is expected overnight.
ISAC is between experiments. Tonight's plan is to restore and check the tune to the yield station once protons are restored so that the yields of Li isotopes can be checked tomorrow morning. Once that's complete, the tune to βNQR will be restored and checked before delivery to the next experiment (hopefully by mid-day or so). — Morton
07:43, 25 March 2010 (PDT)
All three beamlines are now online: BL1A (~105 µA), 2A (10 µA), and 2C4 (~35 µA). The beam energy in both 1A and 2A is 480 MeV. The 2A and 2C4 currents will both be increased over the next few days as targets improve, etc.
A target scan on BL2A will likely be carried out at some point today. Otherwise beam tuning is still in progress. — Morton
20:43, 23 March 2010 (PDT)
Beam is currently running down BL1A and 2C4 (~100 µA and 25 µA, respectively). The 2C4 current is limited by STF water conductivity and will be increased as that improves. ISAC is not expected to request protons down BL2A until late Wednesday at the earliest.
The cyclotron is currently delivering protons at 500 MeV. Depending on how startup proceeds, the beam energy may be reduced to 480 MeV for the start of this running period in order to test the machine stability and production yields on the different beamlines at this energy. Running at 480 MeV reduces the cyclotron spills (as the H- beam makes fewer turns at high energy) which, in turn, reduces activation due to scattered beam. If we can run at 480 MeV on a routine basis, it would reduce the fields in the vault during shutdown allowing for work to begin sooner in shutdown with less dose to those doing the work. — Morton
16:17, 18 March 2010 (PDT)
And we're back.
We're approaching the end of shutdown. The cyclotron is under vacuum, the main magnet is on, and both the RF and the inflector are at or near operating voltage. ISIS is running and the tuning effort is underway; the hope is to inject beam into the cyclotron within the next couple of days. Extraction down BL1A will follow, with extraction down BL2A planned for next week.
Regular beam delivery reports will commence next week. — Morton